Hangzhou Huihe Equipment Co. Ltd:2013-11-27
Jacketed kettle is widely applied in food processing such as candy, medicine, dairy, alcohol, cake, sweetmeat, beverage, can, etc. It can be used to boil soup, cook, stew and porridge in some large restaurants and canteens.
Jacketed kettle finished product figure
After introduce the applied range of jacketed kettle, Huihe machine introduce to you the jacketed kettle installation, use and maintenance method.
Firstly, first introduces the installation method of the jacketed kettle is as follows:
1. Tighten the stretcher two set screws, rocking-turn kettle body, at the ends of the inlet pipe and outlet pipe does not allow with pan rotation.
2. Installed finished, the jacketed kettle with agitator, should be done a free trial shipment inspection, to the transmission parts working properly before put into production use.
Jacketed kettle with agitator finished product figure
3. After admission, such as leakage, joint can tighten nut, until don't leak.
The next to introduce the jacketed kettle using method is as follows:
1. Using steam pressure it shall not exceed quota work pressure for a long time.
2. When admission, should slowly open valve, until the required pressure, condensed water outlet of the cut-off valve, such as with a hydrophobic, it should always be open the valve; If no drain device, first open the valve until have vapor overflow and close the valve, keep open degree in a small amount of water vapor overflow.
3. To the safety valve, it can be used according to the user's own vapor pressure, adjust itself.
4. In the course of steam jacketed kettle, it should often pay attention to the change of steam pressure, with admission valve timely adjust.
Steam jacketed kettle finished product figure
5. Stop after admission, pot should be straight cock open, after more than water.
6. Tilting jacketed kettle and jacketed kettle with agitator, in each class before use, it should be in the rotating parts; On top of the jacketed kettle with agitator of decency, recommended use ingredient; all other adopt 30 #, 40 # machine oil.
Tilting jacketed kettle finished products figure
Finally introduce the maintenance method of the jacketed kettle is as follows:
1. Into the steam pipe and outlet pipe joint leakage, he elected tight nut does not solve the problem; the packing should be added or replaced.
2. Pressure gauge and relief valve should be check regularly, if have defective switch and repair in time.
3. After using 50 hours of reducer, it should off lubricating oil should be removed, use kerosene or diesel wash, add 30 #, 40 # clean engine oil, use after 150 hours, second time to change oil, visible details, after each use oil change to 1000 hours or so.
4. Flake rust-proof oil, it should besmear to brush in time, besmear outside pot of paint, we suggest to use X55-3 aluminum ethylene water resistant paint.
5. This pot uses five years later; it is recommended that safety hydraulic pressure test, after hydrostatic test of the time interval, according to the requirements of the technical department.
Hydrostatic test pressure P water according to the following situation:
When the rated working pressure P amount < 0.6 MPa, P = 0.15 MPa water;
When the rated working pressure P = 0.6-0.8 MPa
P water = P amount + 0.3 MPa
6. The pot body outer use 4.0 ~ 5.5 mm thick steel plate manufacturing, steel grade A3, When the outer pot corrosion thinning after many years to less than 2 mm, should stop to use.
7. Jacketed kettle stainless steel welding and other stainless steel welding joint, it should use stainless steel electrode the 102, 107, 132, 137, it should not be using other brand
- The difference between steam heatin...
- Horizontal autoclave operation matt...
- What issue should be payed attentio...
- Daily use of fermentation tanks' fi...
- Simply discuss how fermentation tan...
- The difference between tilting jack...
- Parsing using and maintenance metho...
- Differences between Vertical Colloi...
- Working principle of colloid mill
- How much does it cost to order the...
- Application difference between coll...
- How to determine the time of using ...
- Sterilization pot
- Colloid mill
Add:33 Tangkang Road, Yuhang District, Hangzhou City, China
Tel : +86-571-86578098
Fax : +86-571-81604276
E-mail : manager@hhmachine.cn
QQ:2355663251 Phone/Wechat/Whatsapp:
+86 15268116877
Skype: huihemachine
QQ:2355663252
MSN:huihemachine@outlook.com